| Activity | Predecessor | Duration (in days) |
| A | - | 6 |
| B | - | 4 |
| C | - | 7 |
| D | ABC | 5 |
| E | ABC | 6 |
| F | D | 9 |
| G | E | 4 |
| H | FG | 8 |
| I | FG | 6 |
| J | H | 7 |
FG
F starts from D & G starts from E;They start from different nodes, and there is no repetition of either F or G,therefore heads of F&G should be merged.
To analyses ABC we need to break this into three pair of AB, BC & AC
AB
A & B starts from 1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to B or B to A
BC
B & C starts from 1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either B to C or C to B
AC
A & C starts from 1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to C or C to A
Each pair need dummy, take nay one letter say B, draw DY from A to B & C to B
NWD diagram
CPM
| Critical path | Duration (in days) |
| 1-3-5-7-8-9 | 4-5-9-8-7 =33 |
| 1-2-3-6-7-8-9 | 6-0+6+4+8+7 =31 |
| 1-4-3-5-7-8-9 | 7+1+5+9+8+7 =36 |
| 1-2-3-5-7-8-9 | 6+0+5+9+8+7 =35 |
| 1-2-3-6-7-9 | 6+0+6+4+6 =22 |
| 1-2-3-5-7-9 | 6+0+5+9+6=26 =26 |