Sunday, March 1, 2009

CPM prob-6

Activity Predecessor Duration (in days)
A - 4
B - 7
C - 6
D AB 5
E AB 7
F CDE 6
G CDE 5

AB

A & B starts from  1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to B or B to A

To analyses CDE we need to break this into three pair of CD, DE & CE

CD

DE

CE

NWD diagram

CPM prob-5

Activity Predecessor Duration (in days)
A - 6
B - 4
C - 7
D ABC 5
E ABC 6
F D 9
G E 4
H FG 8
I FG 6
J H 7

FG

F starts from D & G starts from E;They start from different nodes, and there is no repetition of either F or G,therefore heads of F&G should be merged.

To analyses ABC we need to break this into three pair of AB, BC & AC

AB

A & B starts from  1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to B or B to A

BC

B & C starts from  1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either B to C or C to B

AC

A & C starts from  1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to C or C to A

Each pair need dummy, take nay one letter say B, draw DY from A to B & C to B

 

NWD diagram

CPM

Critical path Duration (in days)
1-3-5-7-8-9 4-5-9-8-7           =33
1-2-3-6-7-8-9 6-0+6+4+8+7      =31
1-4-3-5-7-8-9 7+1+5+9+8+7      =36
1-2-3-5-7-8-9 6+0+5+9+8+7      =35
1-2-3-6-7-9 6+0+6+4+6         =22
1-2-3-5-7-9 6+0+5+9+6=26    =26

CPM prob-7

From the following project draw the NMD. Identify the critical path.     Find out the project duration & associated cost. Calculate the total float for each activity.image

NWD diagram

Critical path;

Critical path Duration (in days)
1-2-4-5-6-7-8 3+7+0+6+4+10    =30
1-2-3-5-6-7-8 3+3+5+6+4+10    =31
1-2-5-6-7-8 3+9+6+4+10       =32 - Critical path
1-2-5-6-8 3+9+6+13           =31
1-2-4-5-6-8- 3+7+0+6+13       =29
1-2-3-5-6-8 3+3+5+6+13       =30

 

Project duration 32 days
cost 32*9=288
Normal cost         704
Total cost         992

 

 

Activity Duration EST EFT LST LFT TF
1-2 3 0 3 0 3 0
2-3 3 3 6 4 7 1
2-4 7 3 10 5 12 2
2-5 9 3 12 3 12 0
3-5 5 6 11 7 12 1
4-5 0 10 10 12 12 2
5-6 6 12 18 12 18 0
6-7 4 18 22 18 22 0
6-8 13 18 31 19 32 1
7-8 10 22 32 22 32 0

CPM prob-4

From the following data construct a NWD

Activity Predecessor Duration (in days)
A - 5
B A 9
C A 7
D BC 4
E A 8
F DE 14
G C 12
H FG 6
I H 8

Solution

Let us analysis the various nodes.

BC

B & C starts from A; They start from same nodes, and C is repeated, therefore dummy is required from either C to B.

DE

D starts from BC & E starts from A;They start from different nodes, and there is no repetition of E or D,therefore heads of D&E should be merged

FG

F starts from DE & G starts from C;They start from different nodes, and there is no repetition of F or G,therefore heads of F&G should be merged.

NWD diagram

 

Critical path

Path Duration
   
   
   

Table calculating various matrix

Activity Duration EST EFT LST LFT TF
A (1-2)            
B (2-3)            
C (2-4)            
D (3-5)            
E (2-5)            
F (5-6)            
G (4-6)            
H (6-7)            
I (7-8)            

CPM prob-3

  1. From the following data construct a NWD
  2. Identify the critivcal path & project completions time
  3. Construct a critical schedule
  4. If activity A is delayed by 2 days, find out whether project completion time is affected or not.
Activity Predecessor Duration (in days)
A - 3
B - 1
C A 4
D B 4
E B 5
F D 2
G E 3

NWD diagram

 

Critical path

Path Duration
A-C 3+4     =7
B-D-F 1+4+2  =7
B-E-G 1+5+3  =9 - Critical path

Table calculating various matrix

Activity Duration EST EFT LST LFT TF
A (1-2)            
B (1-3)            
C (2-4)            
D (3-4)            
E (3-5)            
F (4-6)            
G (5-6)            

CPM prob-2

From the following data calculate NWD. Identify the critical path & its duration. Calculate EST, EFT, LST, LFT & TF for each activity.image

NWD Diagram

 

Path Duration
1-2-4-9-10 4+1+5+7               =17
1-3-5-7-8-10 1+6+8+2+5         =22 -Critical Path
1-3-4-9-10 1+1+5+7               =14
1-3-5-6-8-10 1+6+4+1+5            =17

Table showing EST, EFT etc

Activity Duration EST EFT LST LFT TF
1-2 4 0 4 5 9 5
1-3 1 0 1 0 1 0
2-4 1 4 5 9 10 5
3-4 1 1 2 9 10 8
3-5 6 1 7 1 7 0
4-9 5 5 10 10 15 5
5-6 4 7 11 12 16 5
5-7 8 7 15 7 15 0
6-8 1 11 12 16 17 5
7-8 2 15 17 15 17 0
9-10 7 10 17 15 22 5
8-10 5 17 22 17 22 0

CPM prob-1

From the following data calculate NWD. Identify the critical path & its duration. Calculate EST, EFT, LST, LFT & TF for each activity.image

NWD Diagram

 

Path Duration
1-2-5-6 6+7+5                =18
1-3-6 5+6                   =11
1-2-3-6 6+8+6               =20
1-2-3-4-5-6 6+8+5+4+5        =28 -Critical Path
1-2-4-5-6 6+4+4+5           =19
1-3-4-5-6 5+5+4+5           =19

Table showing EST, EFT etc

Activity Duration EST EFT LST LFT TF
1-2 6 0 6 0 6 0
1-3 5 0 5 9 14 9
2-3 8 6 14 6 14 0
2-4 4 6 10 15 19 9
2-5 7 6 13 16 23 10
3-4 5 14 19 14 19 0
3-6 6 14 20 22 28 8
4-5 4 19 23 19 23 0
5-6 5 23 28 23 28 0