Sunday, March 1, 2009

CPM prob-2

From the following data calculate NWD. Identify the critical path & its duration. Calculate EST, EFT, LST, LFT & TF for each activity.image

NWD Diagram

 

Path Duration
1-2-4-9-10 4+1+5+7               =17
1-3-5-7-8-10 1+6+8+2+5         =22 -Critical Path
1-3-4-9-10 1+1+5+7               =14
1-3-5-6-8-10 1+6+4+1+5            =17

Table showing EST, EFT etc

Activity Duration EST EFT LST LFT TF
1-2 4 0 4 5 9 5
1-3 1 0 1 0 1 0
2-4 1 4 5 9 10 5
3-4 1 1 2 9 10 8
3-5 6 1 7 1 7 0
4-9 5 5 10 10 15 5
5-6 4 7 11 12 16 5
5-7 8 7 15 7 15 0
6-8 1 11 12 16 17 5
7-8 2 15 17 15 17 0
9-10 7 10 17 15 22 5
8-10 5 17 22 17 22 0