From the following data construct a NWD
| Activity | Predecessor | Duration (in days) |
| A | - | 5 |
| B | A | 9 |
| C | A | 7 |
| D | BC | 4 |
| E | A | 8 |
| F | DE | 14 |
| G | C | 12 |
| H | FG | 6 |
| I | H | 8 |
Solution
Let us analysis the various nodes.
BC
B & C starts from A; They start from same nodes, and C is repeated, therefore dummy is required from either C to B.
DE
D starts from BC & E starts from A;They start from different nodes, and there is no repetition of E or D,therefore heads of D&E should be merged
FG
F starts from DE & G starts from C;They start from different nodes, and there is no repetition of F or G,therefore heads of F&G should be merged.
NWD diagram
Critical path
| Path | Duration |
Table calculating various matrix
| Activity | Duration | EST | EFT | LST | LFT | TF |
| A (1-2) | ||||||
| B (2-3) | ||||||
| C (2-4) | ||||||
| D (3-5) | ||||||
| E (2-5) | ||||||
| F (5-6) | ||||||
| G (4-6) | ||||||
| H (6-7) | ||||||
| I (7-8) |