CPM prob-6

Activity Predecessor Duration (in days)
A - 4
B - 7
C - 6
D AB 5
E AB 7
F CDE 6
G CDE 5

AB

A & B starts from  1st node; They start from same nodes, and they are not repeated, therefore dummy is required from either A to B or B to A

To analyses CDE we need to break this into three pair of CD, DE & CE

CD

DE

CE

NWD diagram