From the following project draw the NMD. Identify the critical path. Find out the project duration & associated cost. Calculate the total float for each activity.
NWD diagram
Critical path;
| Critical path | Duration (in days) |
| 1-2-4-5-6-7-8 | 3+7+0+6+4+10 =30 |
| 1-2-3-5-6-7-8 | 3+3+5+6+4+10 =31 |
| 1-2-5-6-7-8 | 3+9+6+4+10 =32 - Critical path |
| 1-2-5-6-8 | 3+9+6+13 =31 |
| 1-2-4-5-6-8- | 3+7+0+6+13 =29 |
| 1-2-3-5-6-8 | 3+3+5+6+13 =30 |
| Project duration | 32 days |
| cost | 32*9=288 |
| Normal cost | 704 |
| Total cost | 992 |
| Activity | Duration | EST | EFT | LST | LFT | TF |
| 1-2 | 3 | 0 | 3 | 0 | 3 | 0 |
| 2-3 | 3 | 3 | 6 | 4 | 7 | 1 |
| 2-4 | 7 | 3 | 10 | 5 | 12 | 2 |
| 2-5 | 9 | 3 | 12 | 3 | 12 | 0 |
| 3-5 | 5 | 6 | 11 | 7 | 12 | 1 |
| 4-5 | 0 | 10 | 10 | 12 | 12 | 2 |
| 5-6 | 6 | 12 | 18 | 12 | 18 | 0 |
| 6-7 | 4 | 18 | 22 | 18 | 22 | 0 |
| 6-8 | 13 | 18 | 31 | 19 | 32 | 1 |
| 7-8 | 10 | 22 | 32 | 22 | 32 | 0 |