CPM prob-7

From the following project draw the NMD. Identify the critical path.     Find out the project duration & associated cost. Calculate the total float for each activity.image

NWD diagram

Critical path;

Critical path Duration (in days)
1-2-4-5-6-7-8 3+7+0+6+4+10    =30
1-2-3-5-6-7-8 3+3+5+6+4+10    =31
1-2-5-6-7-8 3+9+6+4+10       =32 - Critical path
1-2-5-6-8 3+9+6+13           =31
1-2-4-5-6-8- 3+7+0+6+13       =29
1-2-3-5-6-8 3+3+5+6+13       =30

 

Project duration 32 days
cost 32*9=288
Normal cost         704
Total cost         992

 

 

Activity Duration EST EFT LST LFT TF
1-2 3 0 3 0 3 0
2-3 3 3 6 4 7 1
2-4 7 3 10 5 12 2
2-5 9 3 12 3 12 0
3-5 5 6 11 7 12 1
4-5 0 10 10 12 12 2
5-6 6 12 18 12 18 0
6-7 4 18 22 18 22 0
6-8 13 18 31 19 32 1
7-8 10 22 32 22 32 0